Analyze cost and on-time performance
Put an hourly cost on work the scheduler already recorded, and see what finished late.
Insights prices the schedule. It takes every task in a date range, multiplies the hours logged against it by two hourly rates you type in, and reports what that work cost, what it made against the budget on the task, and how much of it hit its due date.
The page reads the scheduler's records and writes nothing back. Nothing here changes a job, a task, or a session.
Before you start
- The Scheduling Engine module. Every organization sees the Insights tab whether or not it is licensed, so the tab strip is not proof. See Module entitlement.
- Web only. Neither mobile app has an Insights tab.
- Tasks with hours on them. Insights counts hours operators and machines actually logged, so a schedule nobody has run against produces an empty report. See Start, pause, and complete a job.
- A Budget on the tasks, if you want profit rather than cost. See Job and scheduler fields.
There is no role gate. Anyone who can open Production can open Insights and change the rates.
Open Insights
Open Production, then the Insights tab, at /production?select=insights.
The report opens on the last 90 days, at a labor rate of $35 an hour and a production rate of $50 an hour. Those are defaults in the page, not settings your organization chose.
Production Insights. Requires the Scheduling Engine module and is web only.
Narrow the window and the work
Seven controls sit in the filter bar, and they split into two kinds.
| Control | Where | What it narrows |
|---|---|---|
| Date range | The center pill: 1d, 7d, 30d, 90d, 1y, or Custom with two date fields and Apply | Refetches the report |
| Labor $/hr, Production $/hr | The Options menu | Refetches the report |
| Machines | Filter pill, grouped by department | Filters the rows on screen |
| Jobs, Operations | Filter pills, each with a search box | Filters the rows on screen |
| Search | The magnifier inside the center pill, matching workorder number, title, part, job, operation and machine | Filters the rows on screen |
| All / Done / On Hold | Status buttons in the center pill | Filters the rows on screen |
Only the date range and the two rates go back to the server. Everything else narrows rows the page already holds, so the cards, both charts and the table move the instant you click.
Machines, Jobs and Operations write themselves into the address bar, so a filtered view is a link you can send. Reset, in the Options menu, clears every filter and returns the window to 90 days.
Completion and on-time KPIs
Three cards run across the top. Workorders carries the counts, Financials carries the money, and Hours is a donut splitting total hours into production and labor.
A task is on time when it completed before its due date, or when it has no due date at all. It is behind when it has a due date and either completed after it or is still open past it.
| KPI | Definition | Counts what |
|---|---|---|
| Workorders | Every task in the window after the filters | Tasks, not jobs. A job for 250 of BH-4021 with three operations contributes three |
| Completed | Tasks at status Done | Closed work only |
| Active | Tasks that are neither Done nor Approved | Open, In Progress and On Hold |
| Completion | Completed ÷ Workorders | The whole window, not a rolling rate |
| On-time | On time ÷ (on time + behind) | Every task carrying a due date, plus every task carrying none |
| Losing money | Share of tasks whose profit is below zero | Needs budgets to mean anything |
| Margin | Total profit ÷ total budget | The small percentage under the Financials number |
Why don't Completed and Active add up to Workorders?
A task at status Approved counts in neither. It stays in the Workorders total and it lowers Completion, so a plant that approves tasks after closing them reads as less complete than it is.
A task with no due date counts as on time.
It lands in both halves of the on-time fraction, so a board where half the work was never given a due date reports an on-time rate it did not earn. Check the Due date column before you trust the number. See Job and scheduler fields.
Completion and on-time KPIs across the period.
Set hourly rates
Select Options at the right of the filter bar. It holds two fields.
- Enter Labor $/hr, the hourly cost of an operator. It opens at
35. - Enter Production $/hr, the hourly cost of a machine running. It opens at
50. - Select Apply, or press Enter in either field.
A blue dot on the Options button means a rate is typed but not applied. Reset, beside Apply, returns both fields to the defaults and clears the filters with them.
The rates are not saved.
They belong to the report, not to your organization, so they return to $35 and $50 on every page load and nobody else sees the numbers you typed. Write your two rates down somewhere your team can find them, or two people will price the same week differently.
Use fully burdened hourly cost, and use one pair of rates for the whole plant. Fully burdened means wage plus benefits, overhead and downtime allowance for labor, and machine cost plus power, tooling and floor space for production.
Insights applies one labor rate and one production rate to everything in the window by design, so there is no per-machine rate to argue about. A per-machine rate that is really a guess turns every machine comparison into a comparison of guesses.
Setting hourly rates. Use fully burdened cost, and set them once for the whole plant.
The cost model
A task's actual is what it cost: the hours recorded against it, priced at your two rates. A task's budget is the dollar figure typed on the task when it was created, which is what you expected to be paid or to spend. Profit is the difference.
| Input | Set on | Unit | Used in |
|---|---|---|---|
| Labor $/hr | The Options menu on this page | Dollars per hour | Labor cost, Total cost, Labor $/unit, Profit |
| Production $/hr | The Options menu on this page | Dollars per hour | Production cost, Total cost, Production $/unit, Profit |
| Labor hours | Sessions operators logged against the task | Hours | Labor cost, the Hours donut |
| Production hours | Machine time recorded against the task | Hours | Production cost, the Hours donut |
| Budget | The task, in Create Workorder or inline on the scheduler board | Dollars | Profit, Margin, the Budget bar |
| Units | The task's good count | Parts | The two per-unit columns, Profit/u |
Total cost is labor cost plus production cost. Profit is budget minus total cost, and margin is total profit over total budget across the window.
For example, OP20 Turn on job BH-4021 logs 6.0 labor hours and 9.5 production hours. At $35 and $50 that is $210 of labor and $475 of production, so total cost is $685. Against a $900 budget the task shows $215 profit and a 23.9% margin, and 400 good parts make that $1.71 profit a unit.
No budgets on your tasks?
Then profit and margin have nothing to subtract from, and the Financials card reads as pure loss. Use Total cost, Labor cost and Production cost on that card and ignore the large number above them until budgets are in.
Budget versus actual
Financials: Profitability, the column chart below the cards, is where cost meets the quote. One column per bucket, bucketed on the date each task was created. The Weekly and Monthly toggle at its top right also moves the Volume chart above it.
| Series | Color | Shows | Visible by default |
|---|---|---|---|
| Budget | Gray | The bucket's total quote, drawn as a wide bar behind the rest | No. Select it in the legend |
| Production cost | Dark orange | Machine hours priced at Production $/hr | Only when no task in the window has a budget |
| Labor cost | Light orange | Operator hours priced at Labor $/hr | Only when no task in the window has a budget |
| Profit / Loss | Green, turning red below zero | Budget minus total cost, stacked on the cost | Only when at least one task has a budget |
The chart reads your data before it draws. Give one task a budget and it switches from a cost breakdown to a profit stack, so two organizations looking at the same chart can see different series. Select Budget in the legend to put the quote behind the stack, and the gap between the gray bar and the colored one is the variance.
The largest gap is the job worth opening. A week where production cost runs long against a flat budget usually means the machine took longer than the quote assumed, which the Production / Labor (h) column in the table below will confirm.
Budget against actual. The largest variance is the job worth investigating.
You do not need this page to know whether you are late. On-time is visible on the scheduler board, where an overdue task is marked in place.
Insights exists to put money on it. See Plan jobs on the scheduler board.
The operations table
Details: All operations at the foot of the page is one row per task, 20 rows a page, sorted newest first. Select any header to sort by it.
Three of its columns pack two numbers each, colored dark orange for production and light orange for labor: Production / Labor (h) draws a bar for each, scaled to the largest value on the page rather than in the whole report; Production / Labor Cost prices those hours; and Production / Labor $/unit divides by good count and adds a donut showing production's share of the cost. Profit and Profit/u are green at or above zero and red below.
The Group pill above the table offers None, Job and Asset. Grouping moves that column to the front, keeps each group's rows together, and adds a totals row per group covering every matching row rather than only the page on screen. Group by Job to find the job that lost money, and by Asset to find the machine that keeps eating hours.
The operations table, and its CSV export.
Export
Export CSV, at the top right of the table, downloads every row your filters match in the sort order on screen, not only the visible page. With Group set to None it downloads at once. With Group set to Job or Asset it opens a menu offering Operation rows, Totals by job or Totals by asset, and Rows + totals.
Column lists for all three layouts are in Production Insights CSV. The file carries the rates you applied, baked into the cost columns, so label it with them before you send it on.
When the report is empty
| Symptom | Cause | Fix |
|---|---|---|
| No insights available for the selected range. | No task was created inside the window | Widen the date range before you suspect the data. A new board often has nothing in the last 90 days |
| The cards read zero and the charts are blank | The filters exclude everything | Select Reset in the Options menu, then reapply one filter at a time |
| No workorders match the current filters. under the table | The search box or a status button is still narrowing rows | Clear the search with the ✕ inside the pill, and select All |
| Not enough date data under a chart | The matching tasks carry no creation date, so nothing can be bucketed | Check the range. An ERP import that skipped dates also causes it. See Import a schedule from your ERP |
Every cost column reads $0.00 | Both rate fields are empty, so nothing is priced | Reopen Options, enter both rates, and select Apply |
| Cost is zero but the work ran | No session was ever logged against the task, so there are no hours to price | See Start, pause, and complete a job |
| Failed to load insights. | The request for the report failed | Select Retry. If it repeats, narrow the range: a year at a busy plant is a large request |
See also
Historical, at /production?select=historical_report, charts good parts and scrap across days, weeks, months, quarters or years, then breaks the total into one card per operation and one row per machine that ran it. Every Last N preset ends at the last completed period, so this week never competes with a full one. Show Scrap adds a second red column beside each period's good column, and only scrap logged against a job reaches it. Actions downloads the view as CSV or a server-rendered PDF, or emails it now or on a cadence.
The scheduler board at /production?select=scheduler shows one production schedule in five views: List, Table, Gantt, Kanban and Calendar. Table is the default and the only view with a CSV button. Grouping by asset, job or operator changes what the rows and columns mean in every view but Calendar. Dragging work between machines, editing in place and linking dependent tasks all write straight to the work order and revert on screen if the write fails. The Gantt carries Sequence view, Working hours mode, the work-sessions strip, unscheduled chips and the capacity lane.